Schedule Risk Agent

LRLR (엘알엘알) · Hackathon entry · Updated 10 November 2026

See what changed, what matters, and what needs attention, in one evidence-backed schedule report. Schedule Risk Agent compares this week's construction schedule with last week's and tells the project team which tasks slipped, which became critical, and what to check first.

Demo video · 2:56Schedule Risk AgentBuilt for construction. Reusable across industries. Delivered by MSPs.

The video plays from YouTube when you press play. · Entry on Devpost ↗

Why we built it

Every week, construction teams export a new Microsoft Project or Primavera P6 schedule. Hundreds of linked activities move a little; one of them quietly loses its last day of float and the completion date slips. Large contractors pay planners and specialist tools to catch this. Smaller firms often have no planner, so nobody looks until the delay is visible on site.

The same firms already pay an IT service provider (an MSP) to run their IT. Schedule Risk Agent lets that provider add a weekly schedule review to the contract and run it for many customers at a known cost per report. Built for construction, reusable across project-driven industries, delivered by MSPs.

What it does

The MSP console: customers, reports this month, estimated cost per report and run history
The MSP console: customers, weekly runs and the estimated cost of each report.

How it's built

Deterministic analysis comes first: the schedule file is read with the open-source MPXJ library, and dates, float and critical flags come from the scheduling tool's own values. Then an agent built with Strands Agents runs on Amazon Bedrock AgentCore Runtime, picks what to check with its schedule tools, and Claude on Amazon Bedrock writes the report. AgentCore Memory keeps each customer's history, and AgentCore Gateway offers the same tools over MCP for an MSP's own copilot. Everything is deployed by CloudFormation from GitHub Actions.

Architecture: MSP console, customer portal and MSP copilot call an AWS Lambda API, which runs a Strands agent on Amazon Bedrock AgentCore Runtime with Gateway and Memory; Claude on Amazon Bedrock writes the report; files and runs are kept in S3 and DynamoDB; EventBridge Scheduler runs it every Monday.
Architecture, as shown in the demo video.

What we measured

These are our own tests on public and synthetic schedules, not customer validation. It reports and explains risk; it does not predict the probability of a delay.

한국어 소개 In Korean

Schedule Risk Agent는 LRLR이 AWS Agentic MSP Hackathon(Devpost)에 낸 출품작입니다. 제출을 마쳤고, 심사는 2027년 1월 5일부터 22일까지, 결과 발표는 1월 28일 전후입니다.

건설 현장은 매주 Microsoft Project나 Primavera P6 공정표를 새로 뽑습니다. 수백 개 작업이 조금씩 밀리다가, 그중 하나가 여유일을 다 써 버리면 준공일이 밀립니다. 큰 건설사는 공정 담당자와 전문 도구로 이걸 잡지만, 작은 회사는 공정 담당자가 없어서 현장에서 지연이 보일 때까지 아무도 모르는 경우가 많습니다.

Schedule Risk Agent는 이번 주 공정표를 지난주와 비교해 준공일이 얼마나 움직였는지, 어떤 작업이 새로 주공정에 들어왔는지, 어떤 점검 항목을 통과하지 못했는지 정리한 보고서를 씁니다. 모든 숫자는 원본 파일이나 정해진 계산으로 추적되고, 알 수 없는 건 추측하지 않고 N/A로 씁니다. 에이전트는 더 볼 필요가 있는 위험만 골라 무엇이 그 작업을 붙잡고 있는지 확인하지만, 원인을 사실처럼 단정하지는 않습니다.

이 서비스는 이미 고객사의 IT를 맡고 있는 관리 서비스 업체(MSP)가 매주 여러 고객사에 돌리는 형태로 설계했습니다. 보고서 한 건에 24–36초, AWS 비용은 약 $0.05–0.15입니다. 공개 P6 파일 20개 중 P6 계산값이 저장된 15개에서, 읽어 낸 종료일 1,604개와 여유일 792개가 저장된 값과 모두 일치했습니다.

자세한 내용은 3분 데모 영상과 Devpost 출품 페이지에서 볼 수 있습니다.

AWS, Amazon Bedrock and the other AWS service names are trademarks of Amazon.com, Inc. or its affiliates; Microsoft Project of Microsoft Corporation; Primavera of Oracle Corporation. This is an independent hackathon entry; LRLR is not affiliated with or endorsed by these companies.